If A and B together can complete a work in 18 days, A and C together in 12 days and B and C together in 9 days, then B alone can do the work in ____?

  • A40 days
  • B30 days
  • C24 days
  • D18 days
Show answerHide answer

Correct answer C

Using the concept of work and rate, we can analyze the given information: A+B = 1/18 (work done per day) A+C = 1/12 B+C = 1/9 By adding the first two equations, we get: (A+B) + (A+C) = 1/18 + 1/12 2A + (B+C) = 1/6 2A + 1/9 = 1/6 2A = 1/6 - 1/9 2A = 1/18 A = 1/36 (work done by A per day) Now, we can find B's work per day: B = 1/18 - 1/36 = 1/24 So, B alone can do the work in 24 days.