A contractor estimates that 3 persons could rewire Jamal's house in 4 days. If he uses 4 persons instead of three, how long should they take to complete the job?

  • A2 days
  • B4 days
  • C3 days
  • DNone of these
Show answerHide answer

Correct answer C

Work = Persons × Days = 3 × 4 = 12 person-days With 4 persons: 12 ÷ 4 = 3 days.