If 5 men complete a work in 8 days, how many men are required to complete the same work in 10 days?

  • A2
  • B4
  • C6
  • D8
Show answerHide answer

Correct answer B

- Total man-days = 5 × 8 = 40 - Men needed to do the same work in 10 days = 40 ÷ 10 = 4.