39 men complete a task in 29 days. How long you will take 29 men to do the task?

  • A29 days
  • B39 days
  • C39 days
  • D59 days
Show answerHide answer

Correct answer C

This is an inverse proportion problem. Formula: Men 1 × Days 1 = Men 2 × Days 2 Given: Men₁ = 39 Days₁ = 29 Men₂ = 29 Days₂ =? 39 × 29 = 29 × x x = 39 × 29/29 = 39.