If 15 men do a piece of work in 8 days. How many men will finish it in 10 days?

  • A14
  • B8
  • C12
  • DNone of these
Show answerHide answer

Correct answer C

15 men complete the work in 8 days Total work = 15 men * 8 days = 120 man-days Now, to complete the work in 10 days: 120 man-days / 10 days = 12 men.