60 man can do a work in 40 days. How long will it take 40 men to complete the same work?
Show answer
Correct answer A
Men days 60: 40 40: x 60/40= x/40, 40x= 60* 40 x= 40*60/40, x= 60.
Correct answer A
Men days 60: 40 40: x 60/40= x/40, 40x= 60* 40 x= 40*60/40, x= 60.