It takes 4 men 14 hours to repair a road. How long will it take 7 men working at the same rate?

  • A4 hours
  • B7 hours
  • C8 hours
  • DNone of these
Show answerHide answer

Correct answer C

4 men × 14 hours = 7 men × x hours 56 = 7x x = 56/7 = 8 hours.