If 500 people complete a work in 25 days and they work for 12 days, then 300 people will complete the remaining work in how many days?
Show answer
Correct answer B
Total work = people × days = 500 × 25 = 12500 person-days Work done in first 12 days by 500 people = 500 × 12 = 6000 person-days Remaining work = 12500 - 6000 = 6500 person-days Now 300 people will do the remaining work. Days needed = Remaining work / people = 6500 / 300 = 21⅔ days.