If 20 men can do a piece of work in 8 days, then how many men can finish the same work in 10 days?

  • A15
  • B17
  • C18
  • D16
Show answerHide answer

Correct answer D

20 men complete the work in 8 days Total work = 20 men * 8 days = 160 man-days Now, to complete the work in 10 days: 160 man-days / 10 days = 16 men.