If A can complete a work in 18 days, B in 20 days, and C in 30 days, B and C work together for 2 days and then leave. How many days will A take to complete the remaining work?
Show answer
Correct answer C
B's 1 day work = 1/20 C's 1 day work = 1/30 (B+C)'s 1 day work = 1/20 + 1/30 = 1/12 (B+C)'s 2 days work = 2 × 1/12 = 1/6 Remaining work = 1 - 1/6 = 5/6 A's 1 day work = 1/18 Time taken by A to complete 5/6 work: = (5/6) / (1/18) = 5/6 × 18 = 15 days.