40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days?
Show answer
Correct answer A
Work done by 40 men in 40 days = 1/3 of total work Total work = 3 × (40 × 40) = 4800 man-days Remaining work = 2/3 of total work = 3200 man-days Time left = 50 days Men required = 3200 ÷ 50 = 64 men Additional men needed = 64 − 40 = 24 men Therefore, 24 more men are required.