If 15 men can do a piece of work in 20 days. In how many days can 25 men finish the same work?

  • A14
  • B12
  • C18
  • D13
Show answerHide answer

Correct answer B

15 men × 20 days = 300 man-days (total work) Now, with 25 men: 300 man-days ÷ 25 men = 12 days Verified & Updated.