If 15 men can do a piece of work in 20 days. In how many days can 25 men finish the same work?
Show answer
Correct answer B
15 men × 20 days = 300 man-days (total work) Now, with 25 men: 300 man-days ÷ 25 men = 12 days Verified & Updated.