If 5 workers can finish a task in 4 days, how many days will it take 10 workers to finish the same task?

  • A2 days
  • B4 days
  • C6 days
  • D8 days
Show answerHide answer

Correct answer A

Given: 5 workers → 4 days 10 workers →? days Using the formula: Workers × Days = Constant 5 x 4 = 10 x X 20 = 10x x =20/10 x = 2 days.